This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.
Traffic impacts
      Hwy 169 and Hwy 282 in Jordan project location map
All traffic impacts are tentative and weather dependent. Syndicate St. to/from Hwy 169 is permanently closed.
Current
Road closures
9 p.m. Wed, April 30 through fall
- Creek Ln. to/from Hwy 169 is closed
 
Lane closures
5 a.m. Tue, April 15 through early winter
- Hwy 169 is reduced to one lane in both directions between Hwy 282 and Hwy 21
 
Access changes
5 a.m. Tue, July 1
- Triangle ln. is permanently limited to right in/right out access to/from Hwy 282
 
Upcoming
Information about upcoming traffic impacts will be posted as details become available.
Road closures
7 a.m. Mon, Nov. 10 through spring 2026
- Co. Rd. 9 is closed between Frontage Rd. and 190th St./Valley View Dr.
 
Access changes
7 a.m. Mon, Nov. 10 through late 2026
- Truck traffic exiting and entering Hwy 169 at Co. Rd. 9 is detoured to the Delaware Ave./Co. Rd. 59 interchange
 
About this project
We are partnering with the city of Jordan and Scott County on a project which will include a new Hwy 169 and Hwy 282/Co. Rd. 9 interchange, two bridges (over Hwy 169 and railroad tracks), two roundabouts, pedestrian tunnel, sidewalks, retaining walls, and noise walls.
Summary of work
- Construct new interchange at Hwy 169 and Hwy 282/Co. Rd. 9
 - Build roundabout at the Co. Rd. 9 and Syndicate St. intersection
 - Build roundabout at the Co. Rd. 9 and 190th St./Valley View Dr. intersection
 - Build Co. Rd. 9 bridge over Union Pacific railroad tracks
 - Widen and repair Hwy 169 bridge over Sand Creek
 - Add traffic signal at NB Hwy 169 exit ramp and Hwy 282
 - Build pedestrian tunnel under Hwy 169 and add new trail connections
 - Construct Hwy 169 acceleration and deceleration lanes
 - Build stormwater improvements
 - Create retaining walls along various areas of the project
 - Add noise walls on both sides of Hwy 169, north of Syndicate St. and Creek Lane
 
Project timeline
The following tentative traffic impacts are anticipated and subject to change:
	    Hwy 169 and Hwy 282 in Jordan project staging map
Stage 1: Spring to early summer 2025
- Work begins on Hwy 169 interchange
 - Single-lane Hwy 169 traffic in each direction
 
Stage 2: Summer to fall 2025
- Single-lane Hwy 169 traffic in each direction
 - Roundabout construction at Co. Rd. 9 and Valley View Dr.
 - Co. Rd. 9 remains open
 - Alternating detour for 190th St./Valley View Dr.
 - Construct pedestrian underpass
 
Stage 3: 2026
- Work on Hwy 282/Co. Rd. 9 overpass
 - Single-lane Hwy 169 traffic in each direction
 - Occasional overnight closures of Hwy 169 for bridge work
 - Temporary traffic light at Hwy 169 and Creek Ln.
 - Truck traffic exiting and entering Hwy 169 at Co. Rd. 9 will instead be detoured to Delaware Ave./Co. Rd. 59
 
Stage 4: 2027
- Median and finishing work on Hwy 169
 - Single-lane Hwy 169 traffic in each direction
 - Remove temporary traffic light at Hwy 169 and Creek Ln.
 - Hwy 282/Co. Rd. 9 overpass opens to traffic
 