Sulphur Lake Bridge

Morton

About the project

Project summary

  • Remove the bridge over Sulphur Lake in Morton
  • Remove bridge abutments down to the ground line, then cover with stone riprap to minimize ground disturbance
  • Remove old pavements and cover with topsoil and seeded to restore to a natural condition
  • Retain a short section of the old roadway and convert to gravel to connect the Sulphur Lake site with the DNR river access parking area

Project update

Friday, June 24, 2022

  • This project has been completed.

Accessibility and state highway projects

All MnDOT projects--both new construction and rehabilitation projects -- must include an evaluation to ensure compliance with the Americans with Disabilities Act.

This project is a bridge removal and does not include any ADA accommodations.

Contacts

Al Setrum
Construction Supervisor
320-214-6321

Sandra Schlagel
Public Affairs
320-214-6362