Hwy 24–Annandale

Hwy 55 to Poplar Ave., Wright County

Reconstruct

Crews will reconstruct Highway 24 from Highway 55 to north of Poplar Avenue in Annandale, includes city utilities and pedestrian access improvements.

Detour in Annandale

Hwy 24 detour map
Detour in Annandale, follow signs. Click map for PDF

Motorists

  • Hwy 24/Park St. closed from Oak Ave. to Poplar Ave. until June 27. Detour uses Poplar Ave. and Hwy 55. Detour map, PDF
  • Hwy 24/Oak Ave open from Hwy 55 and Park St.

Pedestrians

Expect segments of sidewalk closures. Follow pedestrian signs and stay out of closed areas. Consider side or back entrances.

Annandale is open

Access will be maintained and open to businesses and residents, however expect changes and gravel surfaces.

Photo image of Road closed barricade sign

Oak Ave./Park St. intersection closed

May 28 Update - Crews will work underground at the Hwy 24 intersection of Oak Ave. and Park St. All area access is closed. Here’s what to expect:

  • Motorists –Follow signs southeast of Oak Ave. along Chestnut St, Pleasant Ave.
  • Pedestrians –Follow signs northwest of Oak Ave. along Birch St., Maple Ave.

Impacts, work stages

April-November

The project will require road, parking and sidewalk closures on Hwy 24 between Hwy 55 and Poplar Ave. in Annandale. Follow directional signs and stay out of closed work areas.

Detour map: Hwy 24 Annandale
Hwy 24 will close and detour in two stages. Click map for PDF

Motorists

Work on Hwy 24 will be done in two stages from April 8 to November.

April 8 to June 27

  • Stage 1 - In progress: Reconstruct and close Hwy 24/Park Ave. between Oak Ave. and Poplar Ave. Detour uses Poplar Ave. and Hwy 55. Map, PDF

Independence Day Holiday Week

  • All open: All lanes and sidewalks along Hwy 24 to be open between June 27 and July 7 for the Fourth of July festivities in Annandale.

July 7 to November

  • Stage 2: Reconstruct and close Hwy 24/Oak Ave. from Hwy 55 to Park Ave. Detour uses Poplar Ave. and Hwy 55

Schedule is tentative and subject to change

About this project

Location map Hwy 24 roadwork in Annandale in 2020
Reconstruct Hwy 24 in Annandale in 2020. Click map for PDF

Summary of work

  • Reconstruct the road with a new asphalt surface, includes parking, side street approaches and entrances
  • Replace curb, gutters and storm sewer
  • Replace underground city utilities, includes water main and sanitary sewer
  • Improve pedestrian access, includes wider sidewalks and approaches