Traffic impacts
Detours and lane closures will be in place once work begins on May 30. Each phase will require a different detour.
Map of the Highway 210 detour starting on May 30. This detour is expected to last for 31 days. Click to enlarge.
Map of the detour of Highway 210 starting on July 5. This work is expected to last 21 days. Click to enlarge.
Map of the Highway 210 detour starting on July 31. This detour is expected to last 32 days. Click to enlarge.
About this project
Hwy 210 box culvert replacements. Click to enlarge.
Summary of work
Poor condition box culverts will be replaced with new box culverts at:
- 0.1 miles east of County Road 23 over the Tamarack River in Wright
- 2.5 miles west of State Hwy 73 over the Tamarack River
- 0.5 miles east of State Hwy 73 over the Island Lake Outlet in Cromwell
- 0.2 miles west of Interstate 35 over Otter Creek
Public meeting
MnDOT and consultants LHB hosted a virtual public meeting on Wednesday, June 30, to discuss the project. Look through the documents presented at the meeting.