About this 2025 project
All lanes open, project complete
Resurfaced and updated 19 miles of Hwy 238 from north of Morrison Co. Rd. 19 in Upsala to Hwy 27 west of Little Falls, Morrison County. MnDOT thanks the public for their patience as we improved the roadway.

Summary of work
- Pave 19 miles of asphalt road surface
- Realign to a T intersection, installed a flashing stop sign, and added a turn lane at Co. Rd 228 in north Upsala
- Northbound Hwy 238 must stop at the T intersection
- Replace or repair 14 underground drainage structures
- South of Co. Rd. 228
- North of Co. Rd. 227 (50th Ave.)
- South of 55th Ave.
- North of 60th Ave.
- South of Dairy Rd.
- North of Dairy Rd.
- North of 40th St.
- North of 80th Ave.
- North of 100th Ave.
- South of 110th Ave.
- South of 80th St.
- South of 90th St.
- South of 95th St - box bridge at Hay Creek
- South of Swan River/120th St.
- Update safety guardrail
- Install new mumble strips and permanent road markings
- Update pedestrian crossing in Elmdale
- Make other necessary repairs