Project schedule
Spring 2019 through September 2019
- Work on non-signalized RCIs at the following Hwy 65 intersections:
- 143rd Ave. 143rd Ave. N.E. in Ham Lake (PDF)
- 153rd Ave. 153rd Ave. (Co. Rd. 61) in Ham Lake (PDF)
- 181st Ave. 181st Ave. N.E. (PDF)
- Signalized intersection at Hwy 65 at the intersection of Viking Blvd. (PDF)
- Curb and gutter and sidewalk on the existing RCI center median at 169th Ave.
April 15 through mid-June 2019
- Work on signalized RCI at the Viking Blvd. (Co. Rd. 22) and Hwy 65 intersection in East Bethel
- Five-day closure of Viking Blvd. (long weekend Thursday through Monday)
- Motorists will encounter lane shifts and narrowed lanes
- EB/WB Viking Blvd. detours (PDF)
- NB/SB Hwy 65 to Viking Blvd. detours (PDF)
Late April through July 3, 2019
- Work on non-signalized RCI at 153rd Ave. (Co. Rd. 61) and Hwy 65 intersection in Ham Lake
- Motorists will encounter lane shifts and narrowed lanes
- Close and detour center median at 153rd Ave.
- Close and detour left turns from Hwy 65 to 153rd Ave.
- Close and detour 153rd Ave. at Hwy 65
- Detour maps: Stage 1 (PDF) and Stage 2 (PDF)
Mid-May through July 2019
- Project work will begin on non-signalized RCI at 181st Ave. N.E. and Hwy 65 intersection
- Motorists will encounter lane shifts and narrowed lanes
- Close and detour center median
- Close and detour Hwy 65 left turns to 181st Ave. N.E.
- Right in, right out only at 181st Ave. N.E.
- Close and detour 181st Ave. N.E. at Hwy 65
- Detour maps: Stage 1 (PDF) and Stage 2 (PDF)
May 28 through early August 2019
- Project work will begin on the non-signalized RCI at 143rd Ave. N.E. and Hwy 65 intersection
- Motorists will encounter lane shifts and narrowed lanes
- Close and detour center median
- Close and detour Hwy 65 left turns to 143rd Ave. N.E.
- Right in, right out only at 143rd Ave. N.E.
- Close and detour 143rd Ave. N.E. at Hwy 65
- Detour maps: Stage 1 (PDF) and Stage 2 (PDF)
August 2019
- Project work will begin on the non-signalized RCI at 169th Ave. N.E./Flamingo Dr. N.E. and Hwy 65 intersection
- Curb and gutter and sidewalk will be completed in the center median on the existing RCI at 169th Ave.
- Motorists will encounter lane shifts and narrowed lanes on Hwy 65
- Close and detour center median at 169th Ave./Flamingo Dr.
- No left turns allowed from Hwy 65 to 169th Ave./Flamingo Dr.
- Right-in, right out only at 169th Ave./Flamingo Dr.
- Short-term, temporary non-peak lane closures on Hwy 65