Construction projects, plans, and studies
Projects completed in 2020
Browse by highway number
Hwys 1–9
Hwy 1 — Red Lake
Reconstruct between Hwy 89 and border with Red Lake Nation
Hwy 1 — Stony River Bridge
Replace bridge at Stony River, grade approaches near County Road 2 west of Isabella in Lake County
Hwy 1 and Hwy 59 — Thief River Falls roundabouts
Construct three roundabouts, frontage road and multi-use trail between Hwy 59 and Kinney Avenue
Hwy 2 — Bagley
Resurface and pedestrian improvements, construct multi-use trail
Hwy 2 — Bena to Ball Club
Resurface between Bena and Ball Club, construct multi-use trail near Bena
Hwy 2 — Crookston
Resurface east of Crookston
Hwy 2 — Deer River
Urban reconstruct on Hwy 2 and 6 in Deer River
Hwy 2 — Marcoux Corner
Resurface westbound lanes between Hwy 32 and Polk County Road 44
Hwy 3 — Empire Township and Farmington
Added roundabout at 170th St. and left turn lane construction
Hwy 5 — Green Isle
Resurface from Fifth Street in Green Isle to Hwy 212
Hwy 5 — Mississippi River to Minneapolis-Saint Paul International Airport
Highway and ramp resurfaced on Hwy 5 from Mississippi River to 34th Avenue
Hwy 6 — Talmoon
Resurface between Talmoon and Itasca County Road 136
Hwy 7 — Victoria
Stabilized the highway and shoulders and installed an improved drainage system with curb and gutters and new shoulders between Merrywood Lane and Waterford Lane on Hwy 7
Hwy 8 — Taylors Falls
Applied a seal coat on Hwy 8 over the St. Croix River
Hwys 10–19
Hwy 10 and Hwy 47 — Anoka and Coon Rapids
Resurfaced Hwy 10 in both directions between Hwy 47 and Hwy 65 and Hwy 47 between Anoka County Road 10 and Hwy 10; Americans with Disabilities (ADA) improvements at the Hwy 47 and County Road 10 interchange and at the Hwy 10/610 and University Avenue (County Road 51) interchange.
Hwy 10 — Detroit Lakes
Intersection improvements at Kris Street and signal installation at County Road 54
Hwy 10 — Glyndon
Pavement repair on eastbound Hwy 10 in Glyndon
Hwy 10 — Wadena
Reconstruct Hwy 10 from Birch Avenue to east of County Road 4 in the city of Wadena, includes sidewalks, accesses and utilities.
Hwy 12 — Cokato
Resurface from Sunset Avenue Northwest to Seventh Street Southeast, update pedestrian sidewalks; reconstruct access and replace signal at Wright County Road 3; update accesses at Dassel-Cokato high school.
Hwy 12 — Maple Plain to Delano
Installed flexible rubber safety poles in center of Hwy 12 and removed trees on state property.
Hwy 12 — Montrose to Delano
Resurface from Zephyr Avenue in Montrose to north of Bridge Avenue in Delano
Hwy 12 and Hwy 22 — Litchfield
Reconstruction of four blocks of Hwy 12 and Hwy 22 through downtown Litchfield.
Hwy 13 — Prior Lake
Reconstructed Hwy 13, constructed turn lanes, installed traffic signal and improved pedestrian crossings
Hwy 14 — Chester drainage repair
Replace two drainage pipes and a box culvert
Hwy 14 — New Ulm gateway
Complete bridge aesthetics and landscaping
Hwy 15 — Hutchinson
Reconstruct and resurface Hwy 15 in Hutchinson
Hwy 18 — East of Brainerd
Replace bridge over Portage Creek west of Hwy 6
Hwy 19 — Morton slope repair
Stabilize slope and repair road on Hwy 19 near Morton
Hwys 20–29
Hwy 23 — Cottonwood to Granite Falls
Resurface Hwy 23 from Cottonwood to Granite Falls.
Hwy 23 — East St. Cloud
Resurface both directions from Benton County Road 1 to Hwy 95 east of St. Cloud. Reconstruct Hwy 23/County Road 8 access as a safer reduced conflict intersection
Hwy 23 — Nemadji River Bridge
Replace Nemadji River Bridge on Hwy 23, 1.6 miles north of County Road 8 in Carlton County
Hwy 23 and I-94 — Waite Park interchange
Add loop ramps to improve access to/from the Hwy 23/I-94 interchange
Hwy 24 — Annandale
Reconstruct from Hwy 55 to Poplar Avenue in Annandale, includes pedestrian sidewalks and city utilities
Hwy 25 — Monticello, and Hwy 210 — Riverton
Install overhead intersection lighting at Hwy 25 at 600th Street/Kjellberg Court in Monticello; Hwy 210 at Crow Wing County Road 12 (Deerwood shortcut) near Riverton. Improves pedestrian and motorist safety.
Hwy 25 — Montrose
Resurface and improve Hwy 25 from Hwy 12 to Seventh Street South, add new multiuse paved trail and install new water and sewer lines. (City of Montrose-led project)
Hwy 28 — Chokio to Morris
Resurface, replace box culverts
Hwy 28 — Sauk Centre
Replace the bridge over Hoboken Creek west of Sauk Centre.
Hwys 28, 29, and 114 — Starbuck Complete Streets
Downtown complete streets reconstruction, resurface, utility replacement, ADA improvements and multi-use trail.
Hwy 29 — Montevideo bridge
Replace bridge on Hwy 29 over North Parkway Drive in Montevideo.
Hwys 30-39
Hwy 30 — Cottonwood County
Resurface from Cottonwood County Road 7 to Hwy 71
Hwy 30 and Hwy 22 — New Richland
Resurface Hwy 30 from Hwy 22 to New Richland; replace two bridges
Hwy 32 — Thief River Falls to St. Hilaire resurfacing
Resurface, pedestrian improvements in St. Hilaire
I-35 — Duluth Lake Avenue Bridge
Resurface Lake Avenue Bridge in Duluth, safety and mobility improvements
I-35 — Harris to Chisago/Pine County line
Concrete pavement work, drainage updates and safety improvements
I-35 — Heath Creek Rest Area
Rest area reconstruction
I-35 — Pine City
Replace the bridges at Hwy 70 and County Road 7
I-35, I-90, Hwy 56 — concrete pavement repair
Concrete pavement repair on I-35 near Faribault, I-90 Stewartville to Austin and Hwy 56 at West Concord.
I-35, I-35E, I-35W North Metro Split — Lino Lakes to Forest Lake
Project included resurfacing the road and replacing bridges
I-35E — Little Canada
Applied a seal coat on southbound I-35E ramp over I-694
I-35E and County Road J/Ash Street Interchange — Lino Lakes
Install traffic signal and lighting at east and west ramps
I-35E, I-35W, and I-35 North Metro Split — Lino Lakes to Forest Lake
Project included resurfacing the road and replacing bridges
I-35W — Richfield
Repaired concrete on I-35W between 66th Street and 76th Street in Richfield
I-35W — Roseville
Applied a seal coat on the County Road 88 bridge over I-35W and on the I-35W southbound ramp over northbound I-35W
I-35W, I-35E, I-35 North Metro Split — Lino Lakes to Forest Lake
Project included resurfacing the road and replacing bridges
Hwy 36 — Roseville
Applied a seal coat on westbound Hwy 36 over I-35W
Hwy 36 — Saint Croix River Crossing
Mitigation for construction of the new Saint Croix River Crossing. Included rehabilitation of the Stillwater Lift bridge, construction of the Upper Loop Trail along Hwy 95 and landscaping along Hwy 95 north of the bridge and in the interchange of Hwy 36 and Hwy 95.
Hwy 36 — Stillwater Lift Bridge
Transformation into a bicycle/pedestrian crossing including repaired steel connections, restored mechanical and electrical components, repaired concrete railings, reconstructed concourse, paint and lighting replacements
Hwys 40-59
Hwy 41 — Chaska
Landscape, reconstructed and expanded road, improved intersection, signals and pedestrian ramps, relocated trail and built underpass for trail between Hwy 212 and Pioneer Trail. Project lead is Carver County.
Hwy 42 — Resurfacing
Resurfacing Hwy 42 from Plainview to the west side of the newly replaced bridge west of Hwy 61
Hwy 47 — Isle to Ogilvie
Reconstruct 22 miles of road surface, improve road access and update drainage between Hwy 27/47 in Isle and Hwy 23 in Ogilvie. Replace two bridges near Ann Lake.
Hwy 47 and Hwy 10 — Anoka and Coon Rapids
Resurfaced Hwy 10 in both directions between Hwy 47 and Hwy 65 and Hwy 47 between Anoka Co. Rd 10 and Hwy 10; Americans with Disabilities (ADA) improvements at the Hwy 47 and County Road 10 interchange and at the Hwy 10/610 and University Avenue (County Road 51) interchange.
Hwy 53 — Virginia
Turn lanes, traffic signal and accessibility improvements at 13th Street, Mount Iron Drive, 12th Avenue West and Second Avenue West in Virginia in St. Louis County
Hwy 53 and Hwy 1 — St. Louis, Koochiching Counties
Intersection improvement, passing lanes project
Hwy 55 — Plymouth bridge
Repaired concrete, replaced joints and made improvements to the barrier on the westbound Hwy 55 bridge over the Luce Line and the railroad tracks.
Hwy 55 — Pomme de Terre Bridge Replacement
Replace the bridge at Pomme de Terre River, southeast of Barrett
Hwy 56 — Taopi to LeRoy
Repaving
Hwy 57 and Hwy 60 — Wanamingo
Intersection roundabout
Hwy 59 — Newfolden
Replace two culverts
Hwy 59 and Hwy 14 — Slope repairs
Stabilize slopes in Lyon, Murray and Redwood counties
Hwy 59 and Hwy 19 — Resurfacing
Resurface 18 miles on Hwy 59 and Hwy 19 in Lyon and Yellow Medicine counties
Hwys 60-79
Hwy 61 — Hastings
Applied a seal coat on Hwy 61 over the Mississippi River between Second Street and North Loop Road
Hwy 61 — Lake City
Hwy 61 reconstruction
Hwy 61 — Winona
Hwy 61 intersection safety improvements
Hwy 63 — Red Wing bridges
Replace the Mississippi River crossing between Red Wing, Minn. and Wisconsin.
Hwy 65 — Isanti
Improve access; install a reduced conflict intersection to improve access at Hwy 65/Cajima St NE, Isanti. (City of Isanti-led project)
Hwy 65 and 41st Avenue — Columbia Heights
Replaced signal system at intersection of Hwy 65 and 41st Avenue Installed audible pedestrian signals and upgraded pedestrian crossing to ADA standards.
Hwy 67 — Morgan
Resurface road. Project led by City of Morgan.
Hwy 71 — Jackson to Windom and Windom to Hwy 30
Resurfacing and bridge replacement
Hwy 71 — Long Prairie
Replace bridge over Long Prairie River in Long Prairie; resurface Hwy 71 one mile north of Long Prairie.
Hwy 71 — Park Rapids
Install truck route signs, install intersection lighting
Hwy 71 — Windom to Hwy 30
Resurfacing
Hwy 72 — Blackduck
Replace three culverts between Blackduck and Kelliher
Hwy 72 — Waskish
Resurface 14 miles of rural Hwy 72 between Waskish and Baudette
Hwy 74 — Bridge replacement
Replace a bridge on Hwy 74 north of Winona County Road 30.
Hwy 75 — Argyle
Resurface and pedestrian improvements
Hwy 75 — Mustinka River Bridge replacement
Replace bridge over Mustinka River; resurface from Fifth Street in Wheaton to Mustinka River
Hwy 75 — Pipestone bridge
Replace bridge on Hwy 75 over Pipestone Creek.
Hwy 75 — Warren
Resurface and pedestrian improvements on Hwys 1 and 75
Hwys 80-99
I-90 — Austin repaving
I-90 repaving
I-90 — Fairmont to Blue Earth corridor preservation
Pavement restoration and bridge rehab
I-90 — Hayward and Oakland Woods rest area
Rest area reconstruction
I-90 — Nodine bridge replacement
Bridge replacement
Hwy 91 — Adrian North
Resurface from Adrian to Nobles/Murray County line
Hwy 91 — Nobles/Murray County line to Russell
Resurface Hwy 91 from Nobles/Murray County line to Russell, replace four bridges, repair culverts, improve sidewalks in Lake Wilson
I-94 — Albany to Sauk Centre
Resurface both directions of I-94 between Albany and Sauk Centre (nine miles) in Stearns County
I-94 — East Metro Interchange (I-694/I-494/I-94)
Reconstructed ramp, built new southbound auxiliary lane from 10th St. to I-94, replaced and/or widened northbound and southbound interchange bridges, added northbound and southbound buffer lanes, constructed ramp merge area and repair pavement.
I-94 — Minneapolis
Resurfaced road and ramps on I-94 between Nicollet Avenue and Hwy 280
I-94 — Minneapolis
Applied a seal coat on I-94 over Franklin Terrace
I-94 — Minneapolis
Applied a seal coat on westbound I-94 off ramp over the CP Rail Road
I-94 — Minneapolis bridge over 17th Avenue
Crews repaired and painted the bridge over the blue line light-rail transit at 17th Avenue
Hwy 95 — Bayport and Lakeland
Repaired pavement, Updated drainage, upgraded sidewalks and curb ramps
Hwy 95/Hemmingway Avenue roundabout — North Branch
Constructed a single-lane roundabout on Hwy 95 at Hemmingway Avenue in North Branch.
Hwy 97 — Forest Lake
Constructed left turn lanes on Hwy 97 at North Shore Trail and at Keewahtin Avenue North.
Hwy 97/Goodview Avenue — Forest Lake
Constructed a single-lane roundabout on Hwy 97 at Goodview Avenue/Eighth Street in Forest Lake.
Hwys 100-199
County Road 101/Central Avenue Bridge over Hwy 12 — Wayzata
Repaired the County Road 101/Central Avenue Bridge over Hwy 12, added left turn lanes, reconstructed approaches, and repaired ramp pavement
Hwy 111, Hwy 22 — Nicollet to Gaylord
Resurface from Nicollet to Gaylord
Hwy 169 and 101st Avenue interchange — Brooklyn Park
The city of Brooklyn Park is constructing a new interchange at Hwy 169 and 101st Avenue
Hwy 169 and Hwy 41 — Scott County intersection improvements
MnDOT and Scott County constructed a new interchange at Hwys 169/41/78 in Jackson and Louisville townships
Hwy 169 — Milaca
Install Reduced Conflict Intersections (RCI) at Mille Lacs County Road 11 north of Milaca, and County Road 12 and County Road 13 south of Milaca.
Hwy 169 — Nashwauk
Construct intersection safety improvements at the intersection of Hwy 169 and Hwy 65 Nashwauk
Hwy 169 — Plymouth
Place concrete barrier on Rockford Road bridge
Hwy 169 — Saint Louis County
Resurfacing Hwy 169 from Hwy 53 to County Road 26 in St. Louis County, incudes northbound Hwy 169 ramp
Hwy 169 — Vineland
Install pedestrian High Intensity Activated Crosswalk System (HAWK) system at Hwy 169/Ataage Dr. in Vineland. Project led by Mille Lacs Band of Ojibwe
Hwy 172 — Baudette
Resurface between Baudette and Wheeler’s Point
Hwy 194 — Central Entrance repaving
Repaving Hwy 194/Central Entrance in preparation of the Twin Ports Interchange traffic detour
Hwys 200-299
Hwy 200 — Laporte
Reconstruct and raise grade
Hwy 200 — Whipholt
Historic restoration at roadside parking area
Hwy 212 — Norwood Young America
Repaved Hwy 212 from Hwy 25/5 to Cologne
Hwy 220 — Oslo
Replace bridges over the Snake and Tamarac Rivers north of Oslo
Hwy 251 — Hollandale
Resurfacing and culvert replacement
Hwy 280 — St. Paul
Applied a seal coat on the University Ave. and Wabasha Ave. bridges over Hwy 280
Hwys 300-694
Hwy 313 — Warroad
Resurface between Warroad and Canada
Hwy 371 — Hackensack to Hwy 200
Resurface between Cass County Road 5 in Hackensack and Hwy 200
I-394 — Minneapolis
Repaired I-394 bridge over Dunwoody Boulevard in Minneapolis.
I-494 — Bloomington to Eagan
Resurfaced trail from the River Bridge to Hwy 13
I-494 and France Avenue — Bloomington
Repaired concrete, installed signals and accessible ramps
I-494 — Mendota to South Saint Paul
Bridge deck resurfaced and auxiliary lane addition
I-494 and I-94 — East Metro Interchange project (I-694/I-494/I-94)
Reconstructed ramp, built new southbound auxiliary lane from 10th St. to I-94, replaced and/or widened northbound and southbound interchange bridges, added northbound and southbound buffer lanes, constructed ramp merge area and repair pavement.
I-694 — East Metro Interchange project (I-694/I-494/I-94)
Reconstructed ramp, built new southbound auxiliary lane from 10th St. to I-94, replaced and/or widened northbound and southbound interchange bridges, added northbound and southbound buffer lanes, constructed ramp merge area and repair pavement.
I-694 and Rice Street — Shoreview, Little Canada, Vadnais Heights
Built a new bridge and an offset single point interchange with three roundabouts