Bridge over Pipestone Creek

About this project Map of Hwy 75 bridge over Pipestone Creek and detour route

 

Summary of MnDOT work

  • Replace bridge on Hwy 75 over Pipestone County Judicial Ditch #1

Traffic Impacts

  • Detour (at right) will be in effect during the project for through traffic
  • Local traffic will be able to access businesses, parks, and homes in Pipestone

Project updates

Sept. 25, 2020

  • Bridge beams have been placed and formwork is ongoing in preparation of the concrete bridge deck pour.
  • Structural backfilling is complete for the north abutment, and ongoing for the south abutment.

Note: due to the project's late start, the estimated completion date is now Nov. 6.

Crews work on the bridge deck forms in preparation for the concrete bridge deck pour.