Hwy 74 bridge rehabilitations

Whitewater State Park

Traffic impacts

Hwy 74 bridge detour map

Detour map

Northbound Hwy 74 motorists trying to access Whitewater State Park should follow this detour route:

  • Turn left on Winona County Road 22 west, which turns into Olmsted Country Road 9
  • Then go right on Olmsted Country Road 10 north
  • Turn right on Olmsted County Road 2 east, which turns into Winona County Road 39
  • This will bring motorists to the north entrance of Whitewater State Park, south of Elba

About this project

Hwy 74 bridge locations map

Map of bridge locations

Summary of work

Starting Feb. 1, 2021 rehabilitation of four historic bridges on Hwy 74 will start. The project is in Whitewater State Park near the south entrance. The road will be closed at the work zone during the project, which is expected to be completed in late October. 

The work on the four bridges includes repair of floors and walls. Starting the project in the winter will make the work under the bridge easier as less water will be flowing than when the snow begins to melt in the spring. There will also be soil work and rock placement around the bridges to prevent erosion. The numbers of the bridges are 8592, 8593, 8594 and 8595.