Wrap-up project
Hwy 23 is open. In spring 2023 crews will return to complete work and motorists can plan for periodic lane closures with flaggers as crews:

- Install permanent road markings
- Pave the multi-use trail and complete concrete sidewalks and curb/gutter in Foley
- Establish turf and complete other tasks to finish the project
- Replace a box culvert at a stream between 13th Ave. and Lord Ave. in Foley
- Hwy 23 detour: Co. Rd. 4 Foley and Co. Rd. 6 Ronneby
- Open access in Foley: Hwy 23 east/west of the hard closure at the stream
- 2023 tentative detour map
Information is subject to change. Work to be complete before July 3, 2023.