BEMIDJI, Minn. – MnDOT, Pennington County and Red Lake Watershed have a combined total of 10 construction projects in the Thief River Falls area this summer. Many projects are well underway and MnDOT reminds motorists to use caution and follow signs in construction zones. Updates on each project, as well as project websites are listed below.

Hwy 1 - roundabouts

  • Construct three roundabouts, frontage road and multi-use trail between Hwy 59 and Kinney Avenue
  • This projects is in Stage 1 and currently removing the surface from Kinney Avenue to Brooks Avenue. Motorists are currently detoured onto First Street West.

Hwy 1 - culvert

  • Replace culvert west of the intersection with Hwy 59
  • Once this project begins, motorists will detour onto 190th Street Northeast and County Road 14

Hwy 1 - resurfacing

  • Resurface between Hwy 219 and Pennington County Road 18 east of Thief River Falls
  • This project is scheduled to begin in August.

Hwy 32 - roundabout

  • Construct roundabout at the intersection with Pennington County Road 8 and County Road 16
  • Crews continue removal of surface and prepare for installation of curb and gutter.

Hwy 32 - culvert

  • Replace culvert south of Pennington County Road 7
  • Detour beginning on June 11. Motorists will use County Road 3, County Road 20 and Hwy 59.

Hwy 32 - resurfacing

  • Resurface between Thief River Falls and St. Hilaire
  • Motorists can expect shoulder closures along Hwy 32 as culvert installation begins June 8.

Hwy 32 - sidewalks, curbs, and gutters

  • Pedestrian improvements in St. Hilaire
  • Crews are replacing sidewalks as well as curb and cutter in St. Hillaire. Motorists can expect lane closures with a flagger.

Pennington County Road 8/Mark Boulevard - bridge

  • Connect road with the construction of a new bridge over the Red Lake River
  • Crews continue working on pouring abutments and construction of the new bridge. There are no traffic impacts.

Pennington County Road 8/Mark Boulevard - roundabout

  • Construct roundabout at Pennington Avenue South/Pennington County Road 17 near Challenger Elementary
  • Beginning June 8, subgrade will be removed. The intersection is currently closed and a detour is in place. Detour onto Greenwood Street, Hwy 59 and 140th Street Northeast.

Westside Flood Damage Reduction Project

  • Construct a diversion channel and drainage infrastructure on the west side of Thief River Falls. Underground storm sewer will be installed along Barzen Avenue and Greenwood Street, along with a new sanitary sewer.
  • Motorists can expect lane closures along Greenwood Street, Oakland Park Road, and Hwy 32

The projects will not all begin at once. MnDOT and its partners have worked together to combine and stage detours to lessen the overall impact on motorists.

Following guidance from state and federal health officials, and to prevent further spread of COVID-19, crews will maintain social distancing practices while working.

Visit the MnDOT website to learn more about each of the projects, find detour maps and sign up for email updates at mndot.gov/d2/projects/2020/thief-river-falls or join the MnDOT northwest Minnesota Facebook group at facebook.com/groups/MnDOTnorthwest

To request an ASL or foreign language interpreter, call 651-366-4720. To request other reasonable accommodations, call 651-366-4718; the Minnesota Relay service toll-free at 1-800-627-3529 (TTY, Voice or ASCII) or 711, or email your request to adarequest.dot@state.mn.us

For traffic and travel information in Minnesota, visit 511mn.org or get the free smartphone app at Google Play or the App Store.

###