St. Croix Crossing aerial view

St. Croix Crossing

Connecting Oak Park Heights, Minn. and St. Joseph, Wis.

St Croix Crossing logo

Construction maps

Bridge piers progress maps

St. Croix Crossing Minnesota approach piers progress map
This map highlights progress on the Minnesota approach piers. These are on land and east of Hwy 95. As of Sept. 10, 19 of 23 total land piers are at full height (black).
St. Croix Crossing river piers progress
With all five rive pier locations built to the height of the crossbeam—connecting the upstream and downstream pier columns—we have updated this map to reflect crossbeam work progress. Each crossbeam requires three concrete pours (see below). As of Sept. 17, one of three pours at Pier 8 is complete, while construction crews anticipate the first concrete pour at Pier 9 will occur in the coming week. At Pier 12, crews continue to tie reinforcement bar – there is approximately 478,000 pounds of rebar in each crossbeam.

Minnesota Hwy 36/95 approach work maps

Full project construction map