Previous Weekly Updates
- November 22, 2010 project update
- November 15, 2010 project update
- November 8, 2010 project update
- November 1, 2010 project update
- October 25, 2010 project update
- October 18, 2010 project update
- October 11, 2010 project update
- October 4, 2010 project update
- September 27, 2010 project update
- September 20, 2010 project update
- September 13, 2010 project update
- September 6, 2010 project update
- August 30, 2010 project update
- August 23, 2010 project update
- August 16, 2010 project update
- August 9, 2010 project update
- August 2, 2010 project update
- July 26, 2010 project update
- July 19, 2010 project update
- July 12, 2010 project update
- July 5, 2010 project update
- June 28, 2010 project update
- June 21, 2010 project update
- June 14, 2010 project update
- June 7, 2010 project update
- May 31, 2010 project update
Project status
May 15, 2007 - Crosstown project begins.
March 2007 - Ames/Lunda/Schafer bids on Crosstown project
June 2006 - Contractor bid letting. No bids were submitted.
March 2006 - FHWA authorizes the project and the project is advertised for bids.
February 2006 - Mn/DOT completes construction plans.
August 2005 - Mn/DOT determines Negative Declaration on the environmental review.
July 2005 - The Federal Highway Administration (FHWA) issues Finding of No Significant Impact for project.
March 2005 - Mn/DOT accepts Appeals Board Recommendations based on denial of municipal consent by the city of Minneapolis.
August 2004 - Mn/DOT receives municipal consent from the city of Richfield.
July 2004 - Mn/DOT publishes environmental documentation.
April 2004 - Mn/DOT submits staff approved layout to the cities of Richfield and Minneapolis.
February 2003 - Mn/DOT hires SRF Consulting Group, Inc. to refine the design concept proposed in 2002, complete the environmental process and prepare final construction plans.

