2017 Construction update week of July 31

Engineer's Weekly Update


by Dave Van Duesen

Monday, July 31
Cells 115/101: Placed micro-surfacing surface course.
Cells X27/X28: Contractor continuing excavation work.
Cells 185-189: Aggregate base work.

Tuesday, August 1
Cells 188-189: Contractor completing aggregate base work.
Cells 185-186: MnROAD and UTEP personnel installed sensors, conducted geotechnical point tests, and IC mapping.
Cells X27/X28: Excavation work.
Cells X05: Pre-fabric installation sensor prep.
Cells X01- 3: Pre-breaking concrete barrier adjacent to data acquisition cabinets for removal.
Cells X38/X39: OMRR personnel laying out FWD test points.

Wednesday, August 2
Cells X27/X28: No excavation work due to overnight rains.
Cells X38/X39: CSM placing shoulder base material.
Cells X05/X06: MPCA working on weir study.
Cells 188/189: UTEP and MnROAD personnel installed sensors and performing geotechnical point testing. IC mapping in the afternoon.
Cells X01-3: Contractor removing concrete barrier.

Thursday, August 3
Raining today. No construction activity.

Friday, August 4
Cells X38/X39: Contractor plans to perform shoulder grading work.
Cells 188/189: MnROAD personnel will be installing subsurface moisture and temperature sensors.            

Look-ahead high points:

  • Paving of the 4.75 mm HMA thinlays on NRRA PM Cells 201 and 215 is planned for Tuesday, August 8.
  • Excavation work and subsurface drain installation in Cells 128/228 will continue next week.
  • Cells 127/227 and 128/228: Subgrade modification (to create a weak condition) is planned for late the week of August 7. Crushed rock and agg base placement is currently planned for the week of August 14.
  • Much of the HMA paving on the mainline and low-volume road is tentatively planned beginning the week of August 14. This includes all shoulder paving and Cells 185/186/188/189.
  • Construction of the NRRA CCPR sections currently planned for week of August 14. First up will be construction of the test strips. These will be done in the Contractor’s plant yard. Details on the location will be provided as the date gets closer. Surface construction (both HMA and double chip seals) is dependent on actual date of CCPR placement.
  • Cells X05: Final cleaning and installation of fabric is planned for Wednesday, August 16 (not Thursday, August 17). Paving is scheduled for Friday, August 18.
  • Traffic is planned to be switched early in September to facilitate construction of the HMA overlays on the original WB I-94 concrete.




Photos

    Cells 115/101: Placed micro-surfacing surface course. Cells 115/101: Placed micro-surfacing surface course.
    Cells 115/101: Placed micro-surfacing surface course. Cells 115/101: Placed micro-surfacing surface course.
    Cells X01-3: Contractor removing concrete barrier. Cells X27/X28: Excavation work.
    Cells 188/189: UTEP and MnROAD personnel installed sensors and performing geotechnical point testing. IC mapping in the afternoon. Cells 188/189: UTEP and MnROAD personnel installed sensors and performing geotechnical point testing. IC mapping in the afternoon.
    Cells 188/189: UTEP and MnROAD personnel installed sensors and performing geotechnical point testing. IC mapping in the afternoon. Cells 188/189: UTEP and MnROAD personnel installed sensors and performing geotechnical point testing. IC mapping in the afternoon.