2017 Construction update week of July 24

Engineer's Weekly Update


by Dave Van Duesen

Monday, July 24
OMRR personnel setting up gas permeameter in prep for in situ aggregate base testing this week.
Cells X85/X86: MnROAD and UTEP personnel performing final installation of subgrade sensors (pressure cells, accelerometers) in prep for aggregate base this week.
Cells X24: CSM installing subsurface drain.
Cells X88/X89: CSM performing final grading and tolerance of grading subgrade.

 

 

Tuesday, July 25
Cell 185: Contractor placing agg base Class 5Q (recycled PCC). MnROAD personnel collected research samples of agg base.
Cell 186: Contractor placing agg base Class 5 (recycled PCC). MnROAD personnel collected research samples of agg base.
Cells 188/189: MnROAD and UTEP personnel performed geotechnical point tests.
Cells 27/28: Milling operations. Much of Cell 27 bituminous had previously been removed by excavation. Millings hauled to stockpile for sizing.
Cells 33-35: Milling operations. Millings hauled to stockpile for sizing.
Cells 2-4: Milling operations. Millings hauled to stockpile for sizing.

Wednesday, July 26
Cells X15/X01: Micro-milling today. Sand patch testing. Post mill profile runs.
Site wide: Contractor cleanup sweeping operations.
Cell 189: Contractor placing Class 6 (recycled PCC/RAP) agg base.
Cells X27/X28: Excavation.

Thursday, July 27
Cells X27/X28: Excavation work.
Cells X01/X15: MnROAD personnel installing sensors in prep for paving tomorrow.

Friday, July 28
Cells 188/189: Contractor placing limestone base material in Cell 188. Blading and compacting. MnROAD personnel collected base samples.
Cells X27/X28: Contractor excavation work.
Cells 215/201: Contractor placed micro-surfacing scratch course.

Look-ahead high points:

  • See the attached look-ahead schedule for the weeks of July 31 and August 7 provided by CSM yesterday at the weekly meeting.
  • Micro-surface surface course on NRRA PM Cells 101 and 115 planned for 7:00 am Monday, July 31.
  • Asphalt paving of the 4.75 mm thinlays on NRRA PM Cells 201 and 215 is planned Tuesday or Wednesday, August 1 or 2.
  • Cells X05: Final cleaning and installation of fabric is planned for Tuesday or Wednesday, August 8 or 9 (not Thursday, August 10). Paving is scheduled for Friday, August 10.
  • Excavation work in Cells 127/227 and 128/228 will continue the week of July 31.
  • Construction of the NRRA CCPR sections is currently planned for mid-August.
  • Disregard the last activity “Common Excavation” in Cells 133-233 and 135-235. This is an error and is not planned.
  • Traffic is planned to be switched early in September to facilitate construction of the HMA overlays on the original WB I-94 concrete.




Photos

    Cells X24: CSM installing subsurface drain.

    Cells X88/X89: CSM performing final grading and tolerance of grading subgrade.

    Cells 33-35: Milling operations. Millings hauled to stockpile for sizing.

    OMRR personnel setting up gas permeameter in prep for in situ aggregate base testing this week.

    Cells 188/189: MnROAD and UTEP personnel performed geotechnical point tests.

    Rap sizer

    Cells 33-35: Milling operations. Millings hauled to stockpile for sizing. Cells X15/X01: Micro-milling today. Sand patch testing. Post mill profile runs.
    Deterioration over old fog line joint after 3/8 inch micro mill. Cells X15/X01: Micro-milling today. Sand patch testing. Post mill profile runs.
    Cells 215/201: Contractor placed micro-surfacing scratch course. Cell 15 scratch course Mix sample
    Cell 15 Tack Coat Cell 15 Thermocouples