DEPARTMENT OF TRANSPORTATION CONSTRUCTION PROJECT |
  |
 |
 |
Annual Project Summary Report - March 1, 2012 (388K pdf)
President Obama signs bill on 3/13/12 that allows St. Croix River Bridge construction
U.S. House, on a 339 to 80 vote, approved the St. Croix River Crossing Project on 3/1/12
Minnesota Governor Dayton sets deadline of March 15, 2012 - 2/21/12
U.S. Senate Passes S.1134 - 1/23/12
Committee on Energy & Natural Resources - Business Mtg on S.1134 - 11/10/11
Committee on National Resources - Markup on H.R. 850 - 10/5/11
Subcommittee on National Parks Legislative Hearing on S.1134 - 7/28/11
Subcommittee on National Parks, Forests and Public Lands Legislative Hearing on H.R. 850 - 5/4/11
Annual Project Summary Report - March 1, 2011 (2,352K pdf)
One Page Summary - 1/3/11 (103k pdf)
Mn/DOT outlines next steps for St Croix River Crossing Project - 10/25/10
E-Updates - June 2010 - (193k pdf)
Foundation Load Test Project - (1,381k pdf) to gather New River Crossing Bridge design data - project was planned for March - June 2010
but is now suspended, pending Corp of Engineer's permitting which considers, the NPS's new section 7(a) review
St Croix River Crossing Project Revised Construction Dates -
6/2008 (13k pdf)
Sierra
Club Complaint against FHWA and NPS:
City
of Oak Park Heights Complaint against State of Minnesota-Mn/DOT:
A complete
listing of documents will remain on file thru 10/18/10 at the Minnesota
State Attorney Generals Office, 445 Minnesota Street, Suite 1800,
St. Paul, MN 55101
The project schedule
is shown at: St
Croix Crossing Updated Schedule - Feb. 18, 2010 (28k pdf)
Next steps for the DOT’s include acquiring right of way, developing the project's
final design and implementing the project's "Prior to Contracts" mitigation
items.
The
Stakeholder Problem-Solving Process
Beginning
in June of 2003, Stakeholder
Group meetings were facilitated by RESOLVE using the Stakeholder
Resolution Process - Operating Agreement. The final meeting of
the entire Stakeholder Group was held on July 17, 2006. Smaller,
issue based, meetings will continue with members of the Stakeholder
Group. Continued
Stakeholder Involvement - (11k pdf)
|
|