MINNESOTA
DEPARTMENT OF TRANSPORTATION CONSTRUCTION PROJECT |
  |
 |
|
Environmental
Process for the
St. Croix River Crossing Project
November 2003
2003
AMENDED SCOPING DOCUMENT/DRAFT SCOPING DECISION DOCUMENT |
December
2003 |
SCOPING
PUBLIC MEETINGS |
March
2004 |
2003
AMENDED FINAL SCOPING DECISION DOCUMENT |
August
2004 |
SUPPLEMENTAL
DRAFT ENVIRONMENTAL IMPACT STATEMENT |

September 2004 |
PUBLIC
HEARINGS |

June 2006 |
SUPPLEMENTAL
FINAL ENVIRONMENTAL IMPACT STATEMENT |

November 2006 |
RECORD
OF DECISION / ADEQUACY DETERMINATION |

December 2006
|
FINAL
DESIGN |

August 2008 |
RIGHT
OF WAY ACQUISITION |
November 2009 |
PERMITTING |

July 2013 |
PROJECT
LETTING |
2013 - 2016
|
CONSTRUCTION |
 |
|