I-94

St Paul, Oakdale, Landfall, Maplewood, Woodbury

Traffic impacts

Map of I-94 project area in St. Paul
I-94 project area. Click map for larger PDF version.

Watch the I-94 Project Construction video series to learn how to navigate the project area this coming construction season. You can also view graphics for tips on driving through the project area.

Current

Drivers should expect lane restrictions in both directions, traffic delays and temporary exit/entrance ramp closures as project work begins in April.

Ramp closures

Early-April through fall
  • NB Hwy 61 to EB I-94
Early-April through early-May
  • WB I-94 to SB Hwy 61/Etna St.
    • Detour: WB I-94 to White Bear Ave. to Burns Ave. to SB Hwy 61/Etna St. See Detour Map.
  • SB Hwy 61/Etna St. to EB I-94
    • Detour: SB Hwy 61 to Burns Ave. to White Bear Ave. to EB I-94. See Detour Map.
  • White Bear Ave. to WB I-94
    • Detour: White Bear Ave. to Burns Ave. to NB Hwy 61 to WB I-94. See Detour Map.
  • Burns Ave. to EB I-94 (McKnight ramp)
    • Detour: McKnight Rd. to Burns Ave. to Ruth St. to Old Hudson Rd. to White Bear Ave. to EB I-94. See Detour Map.
  • McKnight Rd. to WB-I94
    • Detour: McKnight Rd. to Old Hudson Rd. to Ruth St. to WB I-94. See Detour Map.
  • Hudson Pl. to EB I-94 (McKnight ramp)
    • Detour: McKnight Rd. to Burns Ave. to Ruth St. to Old Hudson Rd. to White Bear Ave. to EB I-94. See Detour Map.
  • WB I-94 to Hudson Rd.
    • Detour: Century Ave. to Hudson Rd.
  • Hudson Rd to WB I-94

Pedestrian bridge closure

Mon, April 24 through Mon, May 8
  • The Maple St. pedestrian bridge over I-94 is closed
    • Detour: N. Maple St. to Hudson Rd. to Earl St. to Pacific St.

 

I-94 Road Construction Video Series

Be ready. Know your route.

Watch this video series to learn about the work on I-94 and how to drive the work zone between Mounds Blvd in St. Paul and Hwy 120/Century Ave. in Maplewood beginning spring 2017. The second year of project work begins in April 2017.

Part 1: Be prepared to choose a lane

About this project

Summary of work

  • Resurface eastbound & westbound I-94 between Mounds Blvd. to east of Hwy 120/Century Ave.
  • Build a new auxiliary lane & extend the existing auxiliary lane along eastbound I-94 between the exit to East 7th St. and the entrance from Mounds Blvd.
  • Construct two emergency pull-off sites along eastbound I-94 between the exit to East 7th S. and the entrance from Mounds Blvd.
  • Resurface Hwy 61 from north of Burns Ave. to Hwy 5
  • Create trail connections at McKnight Rd. and Century Ave.
  • Update signals and pedestrian access
  • Build a new noise wall and replace part of an existing noise wall between Conway St. and Maple St.
  • Repair Bridges