Overview
Status
- Project Complete
Location
St. Paul, Minneapolis
Additional Information
- Environmental Assessment - (June 11, 2010)
- Findings of Fact and Conclusion - (September 15, 2010)
Schedule
-
Phase 1(2010) - St. Paul:
-
Phase 2 - Minneapolis: 2011 View the design layout draft for Phase 2
2010: St. Paul from Hwy 280 to Western Avenue
Description
- Resurfaced and repaired the driving lanes
- Reconstructed shoulders
- Improved drainage and lighting
- Repaired bridges
- Provided additional room on the right shoulder for buses.
Quick Links-Phase 2
- I-94 Managed Lanes Study This report outlines recommendations for the I-94 corridor between Minneapolis and St. Paul.
- Noise Advisory Committee
- Project Documents - Environmental Assessment
- Video Showing Roadway Technology This technology will be used in Minneapolis in 2011
Contacts
- Bre Magee
Public Affairs Coordinator
1500 W. County Road B-2
Phone: (651) 234-7502
- Scott Pedersen
West Area Engineer
1500 W. County Road B-2
Phone: (651) 234-7726