Quick Links-Phase 2
- I-94 Managed Lanes Study This report outlines recommendations for the I-94 corridor between Minneapolis and St. Paul.
- Noise Advisory Committee
- Project Documents - Environmental Assessment
- Video Showing Roadway Technology This technology will be used in Minneapolis in 2011
Contacts
-
Kent Barnard
Public Affairs Coordinator
1500 West County Rd. B-2
Roseville, MN 55113
(651) 234-7504 - Bre Magee
Public Affairs Coordinator
1500 W. County Road B-2
Phone: (651) 234-7502
- Minneapolis, 2011
Scott Pedersen
West Area Engineer
1500 W. County Road B-2
Phone: (651) 234-7726


Get email updates 

Overview
Description
- This is a 2 phase project. (Phase 1 - 2010, Phase 2 - 2011) Roadway and ramp resurfacing, lighting, signing and signal loops between Western Avenue in St. Paul and Nicollet Avenue in Minneapolis
Status
-
Begins May 10, 2010
Location
- St. Paul, Minneapolis
Schedule
-
Minneapolis: 2011 View the design layout draft for Phase 2
Project Documents
Environmental Assessment - (June 11, 2010)
Findings of Fact and Conclusion - (September 15, 2010)