Construction noise

Nearby residences and businesses will experience noise, including overnight, during this work. Crews will work to keep noise down, but when they are resurfacing the interstate and the ramps there will be noise.

Upcoming

Information about upcoming traffic impacts will be posted when details become available.

Road closure

10 p.m. Fri, June 28 through 5 a.m. Mon, July 1
  • WB I-94 is closed between Western Ave. and Hwy 280
    • Detour: North on I-35E, west on Hwy 36, and south on Hwy 280

Ramp closures

9 p.m. Fri, June 28 until 5 a.m. Mon, July 1
  • Access to WB I-94 is closed on all ramps between Western Ave. and Hwy 280

About this project

I-94 between Western Ave. and Hwy 280 will be resurfaced in Ramsey County.

Summary of work

  • Repave I-94 from Western Ave. to Hwy 280
  • Repave ramps in the project area
  • Replace and upgrade signal system at Lexington Ave. intersection
  • New accessible pedestrian signals at Cretin Ave. and Vandalia St. intersections
  • New guardrail along the project area
  • Drainage improvements near Cretin Ave./Vandalia Ave. intersection
  • ADA improvements along St. Anthony Ave. and Concordia Ave.