Locations
- I-494/Nicollet Ave. in Bloomington and Richfield
- Hwy 77/Old Shakopee Road in Bloomington
Schedule
- Project Finished: Oct. 7, 2011
Description
- Resurfacing, curb/gutter replacement, sidewalk replacement, drainage improvements and pedestrian ramp repairs
Contacts
- Bre Magee
Public Affairs
651-234-7502
Project Complete
Schedule
- Project began in August
- Project completed in October
Purpose
The project rehabilitated the Nicollet Ave. Bridge and the 2nd Ave. Pedestrian Bridge, extending the life span of both bridges and improving quality for motorists and pedestrians
Description
- Nicollet Ave. Bridge deck was resurfaced and repaired
- Curbs, gutters and sidewalks were replaced on both sides of the bridge
- The 2nd Ave. Pedestrian Bridge was painted, and the stairs and chain link fence were replaced. Guardrails also were updated. (Reopens to peds on Oct. 7)
The Old Shakopee Road Bridge spanning Hwy 77 in Bloomington
This project is complete.
Schedule
- Project began August 22
- Project completed in September
Purpose
The project rehabilitated the Old Shakopee Road Bridge spanning Hwy 77 to extend the bridge’s overall lifespan and improve ride quality.
Description
- Concrete repair
- Pothole repair
- Curb repair
- Sidewalk repair
- Drainage repair