I-35 North Metro Split

Lino Lakes, Columbus, Forest Lake

Traffic impacts

project location map
I-35 North Metro Split project location map
Click map for larger PDF version
.

Current

Lane closures

Early October to mid-November 2017
  • Periodic lane closures on both directions of I-35 between Hwy 97 and Hwy 8
    • Note: Closures will occur during off-peak hours for site preparation

Upcoming

Road closures

7 p.m. Fri, Nov. 3 to 5 a.m. Mon, Nov. 6
  • SB I-35E between I-35 and I-694 will be closed
    • Detour: SB I-35W to EB I-694
    • Note: This is work unrelated to the I-35 North Metro Split project

Future

Spring through summer 2018

  • I-35 long-term lane closures will occur between Hwy 97 and Hwy 8
    • Note: Ramps at Hwy 97, Broadway Ave. and Hwy 8 will remain open

Summer through fall 2018

  • I-35 long-term lane closures will continue between Hwy 97 and Hwy 8
    • Note: Ramps at Hwy 97, Broadway Ave. and Hwy 8 will remain open

Spring through summer 2019

  • Long-term I-35 lane closures will occur between the I-35W/I-35E split and Hwy 97
  • I-35W and I-35E may be reduced to a single lane at times, just south of the split
  • The NB I-35 ramps to and from Hwy 97 will close for approximately one month

Summer through fall 2019

  • Long-term I-35 lane closures will continue between the I-35W/I-35E split and Hwy 97
  • I-35W and I-35E may continue to be reduced to a single lane at times, just south of the split
  • The SB I-35 ramps to and from Hwy 97 will close for approximately one month

About this project

Six miles of I-35 from just south of the I-35 split to a half mile north of Hwy 8 at the Chisago/Washington county line will be resurfaced. Road resurfacing helps to preserve and extend the use of the pavement. The work will also include replacing three bridges.

Summary of work

  • Resurface existing pavement
  • Replace the Hwy 97 bridge over I-35 with a diverging diamond interchange for better traffic flow and improved safety
  • Update crosswalks at Hwy 97 to meet modern accessibility standards
  • Replace the flyover ramp from westbound Hwy 8 to southbound I-35 with a loop ramp
  • Drainage improvements

Schedule

Project staging
Fall 2017
  • Site preparation, including adding temporary pavement and removing trees and bushes in the construction zone
2018
  • Resurface I-35 from Hwy 97 to Hwy 8
  • Construct the north half of new Hwy 97 bridge over I-35
  • Embankment work and general site preparation for the new Hwy 8 bridge/ramp
  • Construct the new I-35W bridge over I-35E (bridge will open to traffic in 2019)
2019
  • Resurface I-35 from the I-35W/I-35E split to Hwy 97
  • Resurface I-35W just south of the split
  • Construct the new Hwy 8 ramp/bridge over I-35
  • Resurface I-35E just south of the split
  • Construct the south half of new Hwy 97 bridge over I-35 and reconstruct all ramps at the interchange