Minnesota Department of Transportation

511 Travel Info

Hwy 77 Minnesota River Crossing

Bloomington, Eagan

Traffic impacts

Map of Hwy 77 Mn River Bridge project area
Click map for larger PDF version.

A significant portion of this work will affect traffic and is likely to result in congestion.

The Hwy 77 bridge work over the Minnesota River will have an impact on transit service routes.  For the most up-to-date bus service schedule changes visit www.mvta.com.

Current

Northbound Hwy 77 right lane closed 9 a.m. through 5 p.m.

  • Southbound Hwy 77 right lane closed 7 a.m. through 2 p.m.
  • Bus shoulders closed over the Minnesota River through late August.

Future

  • Trail bridge closed throughout the project.
  • Long Meadow trail temporary closes.

About this project

Summary of work

  • Replace bridge joints and guardrail
  • Paint bridges and walkway

Cost

  • $3.5 million Connect with us through Twitter Connect with us through YouTube Connect with us through Facebook