Minnesota Department of Transportation

511 Travel Info

Hwy 62, Penn Ave, Xerxes Ave Bridge Reconstruction

Minneapolis

Project complete

The majority of work that will affect traffic is now complete.

Summary of work

  • Removed and replaced the bridge decks, panels and approaches
  • Replaced bridge rails
  • Upgraded pedestrian crossings at ramp intersections to meet modern accessibility standards

Cost

  • $1.6 million

Contacts

Nick Carpenter
Public Affairs Coordinator
nick.carpenter@state.mn.us
651.234.7710

Tony Schrempp
MnDOT Construction Engineer
anthony.schrempp@state.mn.us
651-366-5133