Project complete
Summary of work
- Hwy 61 was resurfaced with bituminous to provide a smoother ride
- The traffic signal at Buffalo Street was replaced and a flashing yellow arrow signal was added to improve safety
- Six centerline culverts were replaced and additional drainage improvements were made
- Centerline and shoulder rumble strips were added to improve safety
- The signal poles at Headwater Parkway were relocated
- The crosswalk across the south side of Hwy 61 approach was eliminated to improve traffic flow
Cost
- $4.5 million
Contacts
Cara Chandler
Public Affairs Metro District
651-234-7508
Marc Briese
East Area Engineer
651-234-7715