Minnesota Department of Transportation

511 Travel Info

Hwy 61 and Hwy 97 Reconstruction

Forest Lake

Traffic impacts

Hwy 61 and Hwy 97 map with future roundabouts
Click map for larger PDF version.

A significant portion of the work will affect traffic and is likely to result in congestion. Expect temporary lane closures and detours as work is completed.

Current

Mar. 29 through late Aug.

  • Both directions of Hwy 61 between the north intersection of Hwy 97/Scandia Trl and 202nd St traffic will be reduced to a single lane on the east side of the road.


    SB Hwy 61 to EB Hwy 97 Detour:
    210th St to Goodview Ave

    • Note: NB Hwy 61 to EB Hwy 97 will be allowed until June 10. After that date, motorists will  also use the detour.
  • Current staging (PDF)

Detours

Due to the nature of this project, there will be a specific detour for motorists and a different detour for trucks, reference these detour maps for more information:

About this project

Hwy 61/Forest Lake Blvd N. between 210th St. and just north of Scandia Trail N. is a heavily traveled road in Forest Lake. This mile-long section of road runs directly in front of Forest Lake High School. MnDOT will be reconstructing the north and south intersections of this segment of highway to enhance traffic flow in the area.

Construction schedule

Spring 2016

  • Shift traffic to finish constructing roundabouts
  • Reconstruct existing Hwy 97 and southbound Hwy 61
  • Pave roundabouts, existing Hwy 97 and Hwy 61
  • Build driveway access for the school
  • Construct pedestrian bridge and trails

2015 construction completed

  • Aligned and graded new northbound Hwy 61
  • Built portions of the south and north roundabouts
  • Set pedestrian bridge piers and land supports
  • Constructed temporary business access road
  • Built temporary crossover area
  • Resurfacing Forest Blvd

Summary of work

  • Remove signals and construct roundabouts
  • Construct a pedestrian bridge
  • Replace storm drains and other infrastructure
  • Improve pedestrian and bicycle facilities
  • Upgrade intersection lighting