Potential Delay

This project is part of a "Fixing America's Surface Transporation Act" from 2015 that provided Minnesota with additional funds to spend on highway projects.

Before project work can begin, MnDOT is required by statute to have authorization from the state legislature before it can spend the extra funds. That authorization has not gone through as of January 2017. Therefore this project may be delayed.

For complete details about the FAST Act and this delay, you may view the notification.

Hwy 50 project map
Click map for larger PDF version.

Proposed summary of work

  • Add right turn lanes at Fountain Valley Golf Club, Berring Ave., Beaumont Ave., Albatross Cir. and EB at Co. Rd. 79
  • Modify intersections at Co. Rd. 80 and Co. Rd. 81
  • Renew signing
  • Resurface Hwy 50 between Hwy 3 in Farmington and Hwy 52 in Hampton
  • Upgrade ADA crossings in Hampton at Co. Rd. 47 and Water St.

Traffic impacts

A significant portion of the work will affect traffic and is likely to result in congestion.

  • Expect temporary lane closures and detours as work is completed
  • All businesses and residences will remain accessible throughout the project