Minnesota Department of Transportation

511 Travel Info

Hwy 47, Hwy 65 Signal and Accessibility Improvements

Minneapolis

Traffic impacts

Hwy 47, Hwy 65 project map
Click map for larger PDF version.

Future

2018

  • Project work continues on five intersections on Central Ave. and University Ave.

About the signal and sidewalk ramp improvements

Summary of work

2018

Reconstruct the signal systems and sidewalk ramps to comply with ADA requirements at five intersections on Hwy 47/University Ave. and Hwy 65/Central Ave.

  • Hwy 47 at Broadway St.
  • Hwy 65 at University Ave.
  • Hwy 65 at Second St. SE
  • Hwy 65 at Spring St.
  • Hwy 65 at St. Anthony Blvd.

2017 project work - complete

  • Completed: Late May through late Sept. 2017

About the signal and sidewalk ramp improvements

Summary of work

Reconstructed the signal systems and sidewalk ramps to comply with ADA requirements at nine intersections on Hwy 47/University Ave. and Hwy 65/Central Ave.

  • Hwy 47 at NE 20th Ave.
  • Hwy 47 at NE 17th Ave.
  • Hwy 47 at NE 13th Ave.
  • Hwy 65 at S 1st St.
  • Hwy 65 at S 2nd St.
  • Hwy 65 at NE 27th Ave.
  • Hwy 65 at NE 22nd Ave.
  • Hwy 65 and NE 20th Ave.
  • Hwy 65 at NE 19th Ave.
  • Hwy 65 at NE 14th Ave.

2016 project work - complete

  • Completed: Aug. through Nov. 2016
Hwy 47, Hwy 65 2016 project work map
Click map for larger PDF version.

About this project

Summary of work

Reconstructed the signal systems and sidewalk ramps to comply with ADA requirements at six intersections on Hwy 47/University Ave. and Hwy 65/Central Ave.

  • Hwy 47/University Ave. and 3rd Ave. NE
  • Hwy 47/University Ave. and 5th Ave. NE
  • Hwy 47/University Ave. and 8th Ave. NE
  • Hwy 65/Central Ave. and 24th Ave. NE
  • Hwy 65/Central Ave. and 29th Ave. NE
  • Hwy 65/Central Ave. and 35th Ave. NE