Highway 41

Chaska and Chanhassen

Traffic impacts

Highway 41 in Chaska project area map

Hwy 41 project area map.

View full-size map

All traffic impacts are tentative and weather dependent. Access to all businesses and residences will be maintained throughout construction.

Upcoming

Information about upcoming traffic impacts will be provided as details become available. Motorists can expect road and lane closures with detours.

About this project

In summer 2023, crews will resurface Hwy 41 and make additional improvements along the highway between Pioneer Trail and Hwy 5 in Chaska and Chanhassen. This work will create a smoother ride and improve safety and accessibility.

Summary of work

  • Resurface Hwy 41 between Pioneer Trail and Hwy 5
  • Replace traffic signal at 82nd St.
  • Add lighting to Hwy 41 at the Oak Ridge Dr. intersection
  • Add curb ramps at 82nd St. and Hazeltine Blvd. to improve accessibility and meet Americans with Disabilities Act Standards
  • Extend guardrail near Lyman Blvd.
  • Reduce erosion and improve drainage