Project complete

Click map for larger PDF version.
About this project
Summary of work
- Reconstruct Hwy 3 from Hwy 149 to Ann Marie Trail
- Resurface Hwy 149 just north of Hwy 3 intersection
- Modify intersection at Co. Rd. 71/Rich Valley Blvd. and adding turn lanes
Project staging
This project occurred in four stages:
- Complete: Stage 1: May 13 to June 28
- Complete: Stage 2: June 29 to Aug. 6
- Complete: Stage 3: Aug. 6 to Oct. 2
- Complete: Stage 4: 15 days under traffic Oct. 3