Minnesota Department of Transportation

511 Travel Info

Hwy 280

St Paul, Lauderdale and Roseville

Traffic Impacts


  • Striping of the roadway continues (in between raindrops)
  • Additional storm water retention pond work is planned in early-September along the east side of Hwy 280 north of Broadway St. Expect a daytime lane closure.


  • The interchange of Hwy 280 and I-35W is now open!
  • Hwy 280 traffic is open to two lanes in each direction of NB and SB Hwy 280 between Broadway St. and Como Ave. with the completion of work on the new concrete median barrier
  • All ramps and loops along Hwy 280 are open at Como Ave. and at Larpenteur Ave.

About this project

Summary of work

  • Repair and resurface northbound and southbound Hwy 280 and shoulders between Como Ave. and I-35W
  • Rebuild the ramps between Hwy 280 and I-35W and adds zipper merge signs for the ramp from northbound Hwy 280 to I-35W
  • Rebuild approach roadway to the Hwy 280 bridge over Como Ave.
  • Construct concrete median barrier
  • Install new guardrail north of Larpenteur Ave.
  • Improve storm sewer system and ponds along Hwy 280