Current

7 p.m. Fri, July 21 to 5 a.m. Mon, July 24

  • The ramp from WB Hwy 13 to WB Hwy 101 and NB Hwy 169 will be closed intermittently
    • Detour: SB Hwy 169 to Canterbury Rd to access NB Hwy 169
  • The ramp from EB Hwy 101 to EB Hwy 13 will be closed intermittently
  • Note: The two ramps will not be closed concurrently.

July 14 through September

  • Four weekends of alternating lane closures are tentatively scheduled for the weekends of:
    • July 14-17 - Completed
    • July 21-23
    • Aug 4-7
    • Aug 11-14

July 10 through September

  • Hwy 13 between Hwy 169 and Washburn Ave. will have off peak weekday and weekend lane closures
  • Note: Weekday work may occur during the daytime hours of 9 a.m. thru 3 p.m. and nighttime work may occur from 7 p.m. thru 7 a.m. the following day.

    Access to businesses will remain open, however, a detour may need to be followed.

About this project

MnDOT, in cooperation with Dakota County, Scott County, the City of Burnsville and the City of Savage, conducted a Hwy 13 Corridor Study to provide updated guidance for transportation improvements along Hwy 13 through Savage and western Burnsville.

This project incorporates some of the short-term recommendations for improvement at the Dakota Ave. intersection.

Summary of work

  • Resurface Hwy 13 between Hwy 169 in Savage and Washburn Ave. in Burnsville
  • Upgrade signals and accessibility (ADA) at Washburn Ave.
  • Lengthen the left turn lane at Dakota Ave.
  • Construct westbound acceleration lane at Dakota Ave.