Highway 13

Spring Lake and Cedar Lake Townships

Traffic impacts

Highway 13 in Spring Lake Township and Cedar Lake Township project location map

Hwy 13 project location map.
Click map for larger version.

All traffic impacts are tentative and weather dependent. All businesses and residences will remain accessible throughout the project. The main detour navigates traffic around the entire project area using Hwy 282, Hwy 21 and Hwy 19 (PNG).

Current

Road closures

5 a.m. Mon, May 2 through mid-summer

Upcoming

Information about upcoming traffic impacts will be provided as details become available. Motorists can expect lane and road closures with detours as work is completed. Hwy 13 will be closed in segments throughout the project area for approximately four months, starting at the north end of Hwy 13.

About this project

Highway 13 in Spring Lake Township and Cedar Lake Township project staging map. Work will be done in three stages.

Hwy 13 project staging map.
Click map for larger version.

The Hwy 13 project includes road reconstruction and the addition of left turn lanes at several intersections. Work will be done in three stages.

As part of this work, Scott County will also be installing a roundabout at Hwy 13 and Co. Rd. 8 this summer. For more about this project, visit Scott County's project webpage.

Summary of work

  • Resurface Hwy 13 between Hwy 19 in Cedar Lake Township and Hwy 282 in Spring Lake Township
  • Construct 8-foot paved shoulders
  • Construct left turn lanes between Co. Rd. 17 in Spring Lake Township and Co. Rd. 64 in Cedar Lake Township at:
    • Co. Rd. 17/Marshall Rd.
    • Co. Rd. 10/205th St.
    • Co. Rd. 64/240th St.