Proposed MnDOT Construction and Traffic Schedule

August 2014 to April 2015 (Stage I)

Canadian Pacific Railway bridge over Hwy 100
Various retaining walls and noise walls between Minnetonka Blvd and Hwy 7 and south of the Canadian Pacific Railway Bridge
Loops and ramps east of Hwy 100, north and south of Minnetonka Blvd; and east and west of Hwy 100, south of Hwy 7


April 2015 to July 2015 (Stage 2)

Minnetonka Blvd Bridge and Minnetonka Blvd between the bridge and Salem Ave
Northbound Hwy 100, between Hwy 7 and Barry Street  
Hwy 100 ramps to and from Minnetonka Blvd
Toledo Ave
Resurface one half of the West 36th St bridge; traffic will be maintained on the opposing side
Complete the Canadian Pacific Railway Bridge
Noise wall on the east side of Hwy 100, north of Minnetonka Blvd


July 2015 to Oct. 2015 (Stage 3)

Complete the Minnetonka Blvd Bridge
Southbound Hwy 100 and associated ramps, between Minnetonka Blvd and 26th St W
All retaining and noise walls between Minnetonka Blvd and 26th Street
Southbound Hwy 100 exit and entrance ramps to Minnetonka Blvd
Hennepin County Regional Railroad Authority pedestrian bridge over Hwy 100
Minnetonka Blvd between Vernon Ave S and Hwy 100
Frontage road between Minnetonka Blvd and Groves Academy


October 2015 to July 2016 (Stage 4)

Hwy 7 Bridge construction
Hwy 7 loop to Hwy 100
Northbound Hwy 100 between West 36th St to just north of Hwy 7
County Road 25 between Hwy 100 and Beltline Drive


July 2016 to October 2016 (Stage 5)

Complete the Hwy 7 Bridge
Complete southbound Hwy 100 between 36th St and just north of Hwy 7
Complete construction of Hwy 7
Noise wall on the west side of Hwy 100 between Groves Academy and just west of Webster Ave
Ramp and loop on west side of Hwy 100, south of Hwy 7