Orange barrels on a highway

Hwy 100

St. Louis Park

Hwy 100 Project Home | Public Involvement | Noise Advisory Committee | Accessibility and ADA | Contacts

Overview

Status:


Location:


Schedule:


Description:


Cost:

 

 


Hwy 100 Reconstruction

 

Project Description

 

Purpose

Needs

See the design option (PDF, 5 MB) moving forward.

Current Schedule

Conduct Noise Study and NAC meetings

October 2011 – April 2012

Traffic Modeling/Operational Analysis review by
city and county  

December 2011 – February 2012

Preliminary Water Resources Design  

December 2011 – April 2012

MnDOT staff approve layout  

April 2012

Public Open House

May 2012

Final layout approved

May 2012

Municipal consent approval process 

May – July 2012

Public Environmental Assessment (EA) released

July 2012

Develop construction plans and specifications

Summer/fall 2012 – September 2014

EA process complete

Early 2013

Right of Way acquisition

May 2013 – September 2014

Open bids and award contract

November 2014

Construction

2015 – 2017

   


Project History and Background:


This segment is the last sub-standard section on Hwy 100 south of I-394 and is one of the most congested freeways in the Metro area. Originally built in the mid-1930’s, it is part of the first beltway around the Twin Cities. A reconstruction project was proposed in 2006, but the estimated costs hindered the project from moving forward. Some low cost improvements were able to be completed in 2007 in advance of the Crosstown/I-35W reconstruction. In 2008 the State Legislature passed the Chapter 152 legislation that identified among other bridges, the Hwy 7 and Minnetonka Blvd bridges as structurally deficient and need for replacement. In addition to the two bridges being identified, the Metropolitan Council’s 2009 Transportation Policy Plan recommended this project for reassessment for potential scope reduction and cost savings.




Connect with us