Minnesota Department of Transportation

511 Travel Info

I-694 Corridor North Central West

Arden Hills, New Brighton, Fridley, Brooklyn Center

logo

Traffic impacts

See current traffic flow information in the St. Paul/Minneapolis area (mobile version).

All dates are weather dependent.

Road closures

May 2 through May 4

  • Eastbound I-694 closed at I-94 for resurfacing.

May 16 through May 18

  • Westbound I-694 between Hwy 10 and Silver Lake Road closed for concrete repairs.

Lane and ramp closures

Beginning the week of April 21

  • Final repair and smoothing of the westbound I-694 lanes between I-35W and Central Avenue (Hwy 65) will begin the week of April 21. Motorists will encounter lane closures and temporary ramp closures as crews complete work on both directions of the interstate. 

 

I-694 Corridor North Central West project map
Click map for larger PDF version.

About this project

Summary of work

  • Resurfaced I-694 and repair concrete between I-35W and Hwy 100
  • Resurfaced all ramps and loops
  • Replaced bridge decks at Hwy 252/I-94
  • Repaired drainage beneath roadway

Cost

  • $21.1 million Connect with us through Twitter Connect with us through YouTube Connect with us through Facebook