Project schedule
I-35W has various lane closures in each direction from April 2019 through November 2021. There are also temporary ramp closures and temporary traffic control on local roads.
2021
- Construction on NB I-35W between Co. Rd. C in Roseville and Co. Rd. J in Blaine
- Construct outside NB I-35W lanes
- Complete remaining noise walls along NB I-35W in Roseville and New Brighton
- 2021 construction staging map (PNG)
Complete
2020
- Work in median of I-35W between Co. Rd. C in Roseville and Co. Rd. J in Blaine
- Construction on NB I-35W between Co. Rd. J in Blaine and Sunset Ave. in Lino Lakes
- Completed NB I-35W lanes
- Constructed noise walls
- 2020 staging map (PNG)
2019
- Cleared trees and brush for construction of noise walls
- Construction on SB I-35W began
- Temporary widening of NB I-35W
- SB I-35W traffic shifts to existing lanes on NB I-35W
- Constructed noise walls