Orange barrels on a highway
News Release
Sept. 10, 2012

Contacts

Location

MnDOT Metro District
Office of Communications
1500 County Rd B2 West
Roseville, MN 55113

 

Search statewide news

 

 

 

Hwy 61 closing at Hastings Bridge postponed
Closures needed to float in the new Hastings Bridge main span

 

(Roseville, Minn.) – The float-in of the new Hwy 61 Hastings Bridge spanning the Mississippi River has been postponed until the week of Sept. 17.


The postponement is necessary as crews continue to make certain that welds and railings on the device that guide the new bridge structure toward its abutments are tested to specification before moving forward with the historic move.


Once rescheduled, the Hwy will remain closed for up to 72 hours as crews move the Main Span of the new Hwy 61 Hastings Bridge into place.  The closure will be weather dependent.


Motorists will be advised to follow the signed detour using I-494, Hwy 52 and Hwy 55.


In addition, there will be other local travel restrictions that will occur.

 

As is expected for the entire project, access to local businesses and residences on both sides of the bridge will not be affected.


Travelers and residents with questions are encouraged to call the Hastings Bridge Project Hotline at 651-775-5244 or visit the project’s web site at www.dot.state.mn.us/hastingsbridge.


For real-time travel information anywhere in Minnesota visit www.511mn.org.

 

 

 

###

 

 

 

Pay Attention or Pay the Price