(Roseville, Minn.) — Repairs and resurfacing of the bridge carrying southbound Interstate 35W traffic to Highway 88 over railroad tracks and two bridges from northbound Highway 88 to northbound I-35W in New Brighton begin Wednesday, July 6. Work includes deck repairs, resurfacing, bridge railing and work on the approach roads. During the project, crews will work ten-hour days, six days a week.
The bridges will be closed to all traffic throughout the project. Motorists will detour on Ramsey County Road D to reach north and southbound I-35W. Weather permitting, work will be completed by late July.
Mn/DOT reminds motorists to SLOW DOWN in the work zone and NEVER enter a roadway that has been blocked with barriers or cones. Please join us in a safety partnership. For statewide traffic, construction and travel information visit www.511mn.org or call 511.
####