Roseville,
Minn.— The Minnesota Department of Transportation (Mn/DOT) will
begin resurfacing Highway 7 from just east of Highway 41 in SHOREWOOD/CHANHASSEN
to County Road 19 in EXCELSIOR at 7 a.m. Monday, May 13, 2002.
Motorists will
see traffic reduced to a single eastbound and westbound lane during
the life of the project, except during rush-hour travel. Both eastbound
lanes will remain open during morning rush hour, and both westbound
lanes will remain open during afternoon rush hour.
Weather permitting,
crews expect to have this resurfacing project completed by
June 1, 2002.
Mn/DOT reminds
motorists to SLOW DOWN in the work zone and NEVER
enter a roadway that has been blocked with barriers or cones. Please
join us in a safety partnership.
For updated
construction information and roadway closures in the metro area,
visit the Mn/DOT web site at www.dot.state.mn.us/metro/construction.