Highway 55/Hiawatha Avenue Construction Staging

Stage
Description
Estimated Cost
Status
1 Grading, surfacing, lighting and signals from Nawadaha Blvd. to E. 31st St. $8.4 million

Began summer of 1988
Completed July 1990

2 Grading, concrete surfacing and bridges from E. 24th St. to I-94 $1.5 million Began summer of 1992
Completed June 1993
3 Grading, surfacing, retaining walls and rebuild bridges from E. 25th St. to I-94 $4.25 million Began fall of 1994
Completed August of 1995
4 Rebuild bridges between E. 24th St. and Franklin Ave. $4 million Began summer of 1995
Completed October of 1006
5 Construct Hiawatha Ave. bridge over Lake St. and retaining walls, grading and temporary bypass $11 million Let* March of 1996
Bridge opened July 22, 1999
6 Grading, surfacing, retaining walls and and pedestrian bridge between E. 32nd St. and I-94 $13.8 million Let June 1998
Completion set for October 2000
7 Grading, surfacing, lighting, construction of two bridges and a tunnel from E. 54th St. to 46th St. $22.2 million Let June 1999
Estimated completion summer 2001
8A Grading, surfacing, lighting, construction of bridge and interchange at Hwy. 62 and from Hwy. 62 to E. 54th St. $1.7 million Let September 1999
Est. completion summer 2001
8B Grading, surfacing, lighting, construction of bridge and interchange at Hwy. 62 from Bloomington Rd. to 43rd Ave. S. $14.2 million Letting May 2000
Est. completion summer 2001