|
Stage
|
Description
|
Estimated
Cost
|
Status
|
| 1 |
Grading, surfacing, lighting and signals from Nawadaha
Blvd. to E. 31st St. |
$8.4 million |
Began summer of 1988
Completed July 1990
|
| 2 |
Grading, concrete surfacing and bridges from E. 24th
St. to I-94 |
$1.5 million |
Began summer of 1992
Completed June 1993 |
| 3 |
Grading, surfacing, retaining walls and rebuild bridges
from E. 25th St. to I-94 |
$4.25 million |
Began fall of 1994
Completed August of 1995 |
| 4 |
Rebuild bridges between E. 24th St. and Franklin Ave.
|
$4 million |
Began summer of 1995
Completed October of 1006 |
| 5 |
Construct Hiawatha Ave. bridge over Lake St. and retaining
walls, grading and temporary bypass |
$11 million |
Let* March of 1996
Bridge opened July 22, 1999 |
| 6 |
Grading, surfacing, retaining walls and and pedestrian
bridge between E. 32nd St. and I-94 |
$13.8 million |
Let June 1998
Completion set for October 2000 |
| 7 |
Grading, surfacing, lighting, construction of two bridges
and a tunnel from E. 54th St. to 46th St. |
$22.2 million |
Let June 1999
Estimated completion summer 2001 |
| 8A |
Grading, surfacing, lighting, construction of bridge
and interchange at Hwy. 62 and from Hwy. 62 to E. 54th St. |
$1.7 million |
Let September 1999
Est. completion summer 2001 |
| 8B |
Grading, surfacing, lighting, construction of bridge
and interchange at Hwy. 62 from Bloomington Rd. to 43rd Ave. S. |
$14.2 million |
Letting May 2000
Est. completion summer 2001 |