Grading & Base

Quality Control/Quality Assurance (QC/QA)


Modified Penetration Index Method

The Modified Penetration Index Method can now be used for compaction acceptance of all granular materials. The Project Engineer must write a Supplemental Agreement to change the compaction method from Specified Density or the former Penetration Index Method to the Modified procedure.