Project photos
June 2013
Construction crews install the maze of reinforcing bar, or rebar, that will strengthen the concrete deck of the south approach, which will support the northbound lanes of Hwy 61 traffic. Once completed, the new Hastings Bridge will service four lanes of traffic.
Crews construct the roadway and north approach of the new Hastings Bridge. Two lanes of traffic—one in each direction—were switched to the new bridge in early June. The process of dismantling the old Hastings Bridge is underway.
Another view of both the old and new Hastings bridges from the south side of the river near the Hastings downtown district. The entire project is slated to be complete in spring 2014, with four lanes of traffic rerouted to the new Hastings Bridge by the end of 2013.





























