August 2012
April 2012
March 2012
February 2012
January 2012
December 2011
![]() |
![]() |
After a wet spring and summer created challenges for the project, excellent fall weather resulted in a flurry of construction and produced this late fall sunset over the Mississippi River. |
A night time view of the construction site with the existing bridge in the background (colors are enhanced). |
![]() |
![]() |
| A close up look at Pier 5 after pier cap work begins. | A November snow falls upon the construction site. |
![]() |
![]() |
| At the north approach, concrete girders are in place between Pier 10 and the north abutment. | Pier 9, complete with pier cap. The top of Pier 10’s pier cap and the massive beams that rest upon it can be seen through the center of Pier 9. |
![]() |
![]() |
| Crews work on the upper reaches of Pier 5 near downtown Hastings. | Even if it’s cold, the work needs to be done. Two crew members pump concrete in winter at Pier 5. |
![]() |
|
| Warm concrete gets delivered to the construction site, then trucked over the causeway and onto a barge before being pumped into the forms. |
South Approach (Fall 2011)
![]() |
![]() |
Pier 5’s foundation girder rebar is formed and ready to be placed before concrete is poured.
|
Digging the trench for new sewer and water lines between the river and 2nd Street. |
![]() |
![]() |
Starting to move Pier 5 foundation girder rebar into place. |
Water overflowing the banks along the north side staging area creates a mirror image of the existing bridge. |
![]() |
![]() |
Pier 9, looking north across the river near Historic Downtown Hastings. |
Pier 9’s foundation with rebar for pier stems (or columns). |


















































































