Location: City of Duluth
Status:
- Work anticipated to begin Monday, April 4, 2011
Cost:
- $40 million completed
- $28 million remaining
Description:
- Pavement replacement
- Bridge replacement
- Bridge repairs
2011 Schedule:
- April - October 2011
Hours of Work:
- Monday - Saturday
- 6 AM - 10 PM
- No Sundays unless authorized
Note: PDF files require Acrobat Reader.

Schedule
2011 Construction Work
- Replace southbound bridge at the ore docks
- Replacement of the northbound I-35 bridge at the paper mill
- Replace southbound pavement from 46th Avenue W to "Can of Worms"
- Replacement of pavement on the Cody Street ramps
- Bridge repair and painting in "Can of Worms" interchange
2011 Traffic Impacts
- Southbound I-35 closure and traffic diversion to northbound lanes from Garfield Avenue to 46th Avenue W (April to October)
- Northbound I-35 closure and traffic diversion to southbound lanes from Central Avenue to 46th Avenue W (April to October)
- Lane closures on northbound I-35 near Cody Street (one month TBD)
- Ramp closures at:
- Cody Street (one month TBD)
- Northbound I-35 to Hwy 2 Bong Bridge (April to October)
- Southbound I-35 to Hwy 2 Bong Bridge (one month TBD)
- 40th Avenue W to southbound I-35 (June)
- Southbound I-35 to 40th Avenue W (June)
- 40th Avenue W to northbound I-35 (August)
- Northbound I-35 to 40th Avenue W (August)
- 27th Avenue W to southbound I-35 (one month TBD)
- Southbound I-35 to 27th Avenue W (April to October)
- Can of Worms (watch for updates on closures)
- Southbound Hwy 53 to southbound I-35 closed (April to October)
- Northbound I-535 to southbound I-35 closed (April to October)