Status
- Work is complete for 2011
- For project information call 218-725-2708
Cost
- $68 million
Description
- Pavement replacement
- Bridge replacement
- Bridge repairs
I-35 South of Duluth
- This construction corridor has its own website. Visit I-35 South of Duluth website.
Note: PDF files require Acrobat Reader.
![]() |

Alternative Routes to Duluth
Trip Planning Information
Motorists are encouraged to plan ahead this summer to avoid the heaviest travel times on Interstate 35 or use an alternative route — especially during holiday or major event weekends.
|
Construction is finished for 2011 and all lanes are open.
All remaining work will be completed in spring 2012 and includes installation of median barrier, bridge painting and deck repair on the ramp from northbound I-535 to northbound I-35. This work will require a three-week lane closure on I-35 and closure and detour of the ramp.
Construction 2011
- Replace southbound bridge at the ore docks.
- Replace the northbound I-35 bridge at the paper mill.
- Replace southbound pavement from 46th Avenue W to "Can of Worms."
- Replace pavement on the Cody Street ramps.
- Bridge repair and painting in "Can of Worms" interchange.
- Bridge painting in the Grand Avenue/Central Avenue area.