Project status: Completed in 2005
Bid Results
- Nov. 19, 2004 bid results (18kb PDF)
- Form 14 Proposal Price
- Duininck Bros (88kb PDF)
- Midwest Contracting (26kb PDF)
- Northern Improvement (59kb PDF)
- Riley Bros (22kb PDF)
- Wanzek Construction (73kb PDF)
RFP Clarifications
- #8, Oct. 12, 2004
- #7, Oct. 8, 2004
- #6, Oct. 6, 2004
- #5, Oct. 5, 2004
- #4, Oct 1, 2004
- #3, Sept 24, 2004
- #2, Sept. 2, 2004
- #1 Aug. 26, 2004
RFQ, Clarifications and Addenda
- Request for Qualifications, May 14, 2004
- Clarification 1, June 4, 2004
- Clarification 2, June 11, 2004
- Clarification 3, June 18, 2004
- Clarification 4, June 23, 2004
- Addendum 1, June 18, 2004
- Addendum 2, June 23, 2004
About the Hwy 10/32 Interchange project
Mn/DOT - District 4 (Detroit Lakes/Morris)
State Project Number: 1401-150
Location
Hwy 10 is a medium priority Interregional Corridor (IRC). Hwy 32 intersects Hwy 10 near Hawley, Minn. in Clay County.
Project Cost
- $8.6 million
Background
- Hwy 10 is a major east-west IRC that parallels I-94 from Moorhead to the Minneapolis-St. Paul Metropolitan area.
- This corridor has experienced significant traffic growth.
Crashes
- Fifteen crashes have occurred at this intersection in the past five years.
- Twelve of the 15 crashes were right-angle-type crashes; the other three were rear-end collisions.
- Four of the right angle crashes involved fatalities.
- In response to the number of crashes, a project was added to the program for construction in 2009.
Funding
- In September 2003, Governor Tim Pawlenty identified this project in his Transportation Finance Bill which is designed to fund critical highway and transportation projects.
- This innovative plan uses internal savings and redeploys existing non-construction resources to finance projects, which accelerated this project by three years.
Construction
- The project was advanced an additional year using design-build contracting.
- Construction then began in 2005.
Project Description
- This project was completed through a single design-build contract that consisted of:
- lowering Hwy 10 by 10 feet
- construction of a bridge on Hwy 32 (Br. #14014) over Hwy 10
- ramps in all 4 quadrants - conventional diamond
- wetland restoration
- a Park and Ride facility
Benefits
- Increased safety for the traveling public with fewer crashes that involve injuries and fatalities
- Easier access for trucks and cars from Hwy 32 to Hwy 10.
- Construction of an interchange that prevents another signal from being added to an IRC route.
- Obtaining a 3.89 benefit/cost ratio for this improvement.
Contact
Trudy A. Kordosky, P.E.