Looking west on the CP Rail Railroad bridge consturction to connect the two embankments to begin after July 4th Concrete box culvert sections waiting to be placed north of the CP Rail Railroad Moving utility lines for construlction of new 185th Street Push-pull scrapers excavting topsoil east of County Road 33
Partially completed embnakment along Highway 55 north toward railroad; pipe to be installed east across the embankment On Highway 55 looking south at new embankment construction Haul road heading south from Highway 55 towards the temporary construction bridge over the NFCR Scraper crossing thte temporary construction bridge over the NFCR
From the north bank looking at the south pier and abutment of the eastbound Highway 23 bridge over the NFCR Forming and placing reinforcing steel on the west abutment of the First Street bridge over Highway 23 Partially completed east abutment on the First Street bridge over Highway 23 Sifting sand out of the rocks for use as riprap at the ends of culverts throughout the project
Driving pile for the north pier of the westbound Highway 23 bridge over the NFCR
Constructing storm sewer between Lake Street and County Road 130