  • There will be a detour of Co Rd 7 during 2019 construction

2018 Project updates

  • Rapid stabilization complete.
  • Grading work complete.
  • Traffic control measures removed.
  • Temporary pavement markings in place.
  • Permanent striping and permanent erosion control (seeding) will take place spring 2019 due to weather conditions.

     

About this project

Project summary 2019

  • Construction of a Reduced Conflict Intersection (J-turn) at the intersection of Hwy 23 and Lyon Co Rd 7 in Marshall

Project summary 2018

  • Construction of Reduced Conflict Intersection (J-turn) at Hwy 23 & Lyon Street in Marshall
  • Construction of restricted left-turn lane at Hwy 23 & Clarice Street in Marshall

Contractor

Cost

  • $1.6 million